Kondisi Pembangkit PLTU Baturaja 30 November 2023
Kondisi Operasi Mesin
STG 1 = ON (0 – 24 )
STG 2 = ON (0 – 24 )
Maintenance
Mekanik
- Cleaning area workshop
- Inspeksi All Weighing conveyor
- Inspeksi kompresor SULLAIR
- Install pipa ceramic liner line transfer ash silo area top main silo
Jalur #3 - Inspeksi ESP Vessel # 5
- Repair screen R/H
- Melakukan penambahan oil block bearing all IDF
- Melakukan Fabrikasi pipa return SC ke Reservoar
Elektrik
- Perawatan Panel Area Cwp
- Check & Repair Speed Sensor speed FWP Pump 3.
- pengukuran kabel power ponton
- perapian kabel ethernet area camney
- Continue perawatan ac area camney, esp dan crusher
- Daily maintenance
SPB
Nihil