Kondisi Pembangkit PLTU Baturaja 9 Desember 2023

Kondisi Operasi Mesin
STG 1 = OFF
STG 2 = ON (0 – 24 )

Maintenance
Mekanik

  1. Finishing ESP #1
  • Reinstall stoper CP yg lepas.
  • Perapihan cover plat flexible Joint area elektroda room
  • Reinstall rapping yang lepas dan rusak ( ganti baru )
    -Cleaning

2. Support Mr.Lee install lock pin Turbine #1

3. Repair Valve venting upper steam drum DN 15 PN 100

  • Ganti gasket

4. Repair manual valve DN 80 PN 100 Steam Blow Boiler #1

  • Ganti gasket Bonet

5. Repair kebocoran pada casing IDF #1 dan IDF #2
6.Repair sand filter #2 dan #3
7.Melakukan repair kebocoran pada discharge pipe dan penambahan Baut flange suction pipe pompa ponton #1
8.Improvement pembuatan pipa udara untuk backwosh pada sand filter #2

Elektrik

  1. Suport team mekanik
  2. Suport team subkon trafo
  • SPB
    Nihil

Progress OH unit#1 PLTU Baturaja, 09 Desember 2023

Boiler#1

  1. Stop Boiler 1, 100%
  2. Cooling boiler, ESP, drain debu ESP, 100%
  3. Cleaning ESP 1 (Drain), 100%
    4.Perbaikan ESP 1, 80 %
    5.Perbaikan Screen Outlet ESP 1, 100 %
    6.Penggantian dan perbaikan Valve DN20 2 Pcs Elv. 26 dekat Drum Boiler #1, 100 %
  4. Kebocoran pipa drain Collection di Elv. 7 Boiler, 100 %
    8.Kalibrasi Sensor Boiler & Greasing SAF dan PAF, 100 %
    9.Kebocoran pipa jalur pasir Syclone arah SWAS Room Boiler #1, 100%
  5. Kebocoran Pipa Downcomer dan Valve Collection Elv.0 Boiler #1 , 100 %
  6. Cleaning Air Heater Boiler 1, 70 %
  7. Cleaning Burner Boiler 1, 100%
  8. Cleaing Nozle Furnace Boiler 1, 100 %
  9. Cleaning Nozle Solar Boiler 1, 100%
  10. Start Boiler 1, 0%

Turbin#1

  1. Stop Turbine #1, 100%
  2. Pengecekan (Perbaikan) Kebocoran Fleksible Joint Oli Governour Turbine #1, 100%
  3. Pengecekan (Perbaikan) rembesan Oli di MSV Turbine #1, 100%
  4. Pengecekan (Perbaikan) gasket HPH Turbine #1, 100%
  5. Pengecekan (penggantian) manual gasket valve bypass Inlet Economizer di Elv. 7 dekat kamar mandi CCR, 100%
  6. Perbaikan Trafo 20KV, 85 %
  7. Cleaning Oil Cooler 1&2, 85 %
  8. Cleaning Air Cooler Generator, 100 %
  9. Start Turbine #1, 0%

Tanpa padam unit

  1. Cleaning sand filter, 80 %
  2. Perbaikan pondasi ring hammer, 25%

Additional work setelah stop unit#1

  1. Repair kebocoran deck area isolator ESP#1, 85%