Kondisi Pembangkit PLTU Baturaja 11 Desember 2023

Kondisi Operasi Mesin
STG 1 = ON (16.52 – 0)
STG 2 = ON (0 – 22 )

Maintenance
Mekanik

I. Daily Jobs
1. Inspeksi kompresor SULLAIR
2. Inspeksi Weighing

II. Over Haule

  1. Finishing Reposisi pipa drain manual vessel #2 & vessel #3
    Penambahan pipa buang
    reinstall cover
  2. Cleaning scrap ex OH ESP #1
  3. Re insulating All item ex OH
    Flexible joint exhaust ducting boiler #1 Elv.0
    Valve drain flash tank DN 50 boiler#1 Elv.7
    Valve FWP Elv.7
  4. Repair Top hoist ESP #2
    Seling kusut

Elektrik

  1. Switching kembali trafo#1masih ada rembesan dalam oli
  2. Support team mekanik
    • SPB
    Nihil

Progress OH unit#1 PLTU Baturaja, 11 Desember 2023

Boiler #1

  1. Stop Boiler #1, 100%
  2. Cooling Boiler, ESP, drain debu ESP, 100%
  3. Cleaning ESP 1 (Drain), 100%
  4. Perbaikan ESP 1, 100%
  5. Perbaikan Screen Outlet ESP 1, 100%
  6. Penggantian dan perbaikan Valve DN20 2 Pcs Elv. 26 dekat Drum Boiler #1, 100%
  7. Kebocoran pipa drain Collection di Elv.7 Boiler #1, 100%
  8. Kalibrasi Sensor Boiler #1 & Greasing SAF & PAF, 100%
  9. Kebocoran pipa jalur pasir Syclone arah SWAS Room Boiler #1, 100%
  10. Kebocoran Pipa Downcomer dan Valve Collection Elv.0 Boiler #1 , 100%
  11. Cleaning Air Heater Boiler #1, 100%
  12. Cleaning Burner Boiler #1, 100%
  13. Cleaing Nozle Furnace Boiler #1, 100%
  14. Cleaning Nozle Solar Boiler #1, 100%
  15. Start Boiler #1, 0%

Turbin#1

  1. Stop Turbine #1, 100%
  2. Pengecekan (Perbaikan) Kebocoran Fleksible Joint Oli Governour Turbine #1, 100%
  3. Pengecekan (Perbaikan) rembesan Oli di MSV Turbine #1, 100%
  4. Pengecekan (Perbaikan) gasket HPH Turbine #1, 100%
  5. Pengecekan (penggantian) manual gasket valve bypass Inlet Economizer di Elv. 7 dekat kamar mandi CCR, 100%
  6. Perbaikan Trafo 20KV, 100%
  7. Cleaning Oil Cooler 1&2, 100%
  8. Cleaning Air Cooler Generator, 100%
  9. Start Turbine #1, 0%
  10. Perbaikan sand filter 1,2 dan 3 45%
  11. Perbaikan pondasi Ring Hammer, 30%

Additional work setelah stop unit#1

  1. Repair kebocoran deck area isolator ESP#1, 100%
  2. Penggantian Spiral Wond Drain Extraction Turbine 1 Elv. 3,5 100%
  3. Penggantian gasket Bypass Steam Turbine 1 Elv. 3,5 100%
  4. Perbaikan transmiter Main Steam Header 2 Boiler 1 100%
  5. Penggantian Valve Sensor Main Steam Turbine 1 100%
  6. Penambalan kebocoran pipa Cooler Generator 1 100%
  7. Perbaikan Dinding Furnice yang rontok 100%
  8. Cleaning Ducting PAF dan SAF Boiler 1 100%
  9. Perbaikan Dumper PAF Inlet Air Furnice Boiler 1 sisi Demin 100%
  10. Repair kebocoran mangkok SteamBlow Boiler 1 100%
  11. Cleaning Water Filter Turbine 1 100%
  12. Perbaikan Pin Getpost Turbine 1 sisi Cooling Tower 100%
  13. Repair kebocoran Gasket Flange main Steam Drum ke Pressure Transmiter Elv.32 Boiler 1 100%
  14. Pengelasan Joint antara sisi A dan sisi B Air Heater PAF bagian Outlet Elv. 11 Boiler 1 100%
  15. Perbaikan kebocoran Ducting SAF dekat leher angsa Elv.0 Boiler 1 100%
  16. Perbaikan Casing Inveler IDFan 2 100%
  17. Perbaikan Casing Inveler IDFan 1 100%
  18. Pemindahan jalur drain manual vesel 2 dan 3 ESP 1 100%
    Alhamdulillah Unit#1 close
    Unit#1 sinkron dengan jaringan jam 16.52