Kondisi Pembangkit PLTU Baturaja 14 Desember 2023
Kondisi Operasi Mesin
STG 1 = ON (0 – 24)
STG 2 = OFF
Maintenance
Mekanik
- Repair ESP #2
r-epair Hopper No.4 5 6
-Pasang siku untuk mencegah debu keluar saat hopper penuh
-Repair deck isolator room
-Repair kebocoran deck elektroda room :
No.5 arah ESP 1 – MPB
No.5 arah mes
No.6 arah ESP 1
-Perbaikan pin CP yang lepas
-Reposisi CP pipa support yg bending - Support tim electrik ganti valve motor steam blow DN 80 PN 100 Elv:32
- Melakukan perbaikan dan improvement jalur pipa udara pada sand filter #1
- Melakukan pengukuran diafragmant oil seal pada IDF
- Melakukan pengecekan dan perbaikan pada check valve vacoom turbine #2
- Flashing all H/E stage #2
Elektrik
- Suport subkon transformer #2
- Suport team mekanik
- Pengecekan transmitter level drumb boiler #2
- Setting ulang LS open close motor valve main steam blow boiler#2
- Suport lighting di super heater cyvlon elv. 26
• SPB
- Konsumable OH plate stell 4 mm 2 lembar
Progres OH unit #2 PLTU baturaja 14 desember 2023
Stop Boiler 2, 100 %
- Cooling boiler, ESP, drain debu ESP 2, 100%
- Cleaning ESP 2 (Drain), 100%
- Pengecekan Isolator dan Heater ESP 2 100 %
- Perbaikan Collecting Plate dan Elektroda, 80 %
- Perbaikan (penggantian) gasket manual valve Superheater Boiler #2 Elv. 32, 100%
- Perbaikan (penggantian) gasket manual valve Bypass MainSteam Boiler #2 Elv. 32, 100%
- Perbaikan (penggantian) manual valve venting MainSteam Boiler #2 Elv. 32, 100 %
- Pengecekan (perbaikan) Valve Steam Blow Boiler #2, 80%
- Pengecekan (perbaikan) sensor level Drum boiler 22, 80%
- Pengecekan Air Heater Boiler 2, 100%
- Cleaning Burner Boiler, 2, 100,%
- Cleaing Nozle Furnace Boiler 2, 100%
- Cleaing Nozle Solar Boiler. 0 %
- Start Boiler 2. 0%
TURBINE - Stop Turbine #2, 100%
- Pengecekan (Perbaikan) rembesan Oli Pilot Tranduser Turbine #2, 0%
- Pengecekan (penggantian) manual valve bypass Inlet Economizer di Elv. 7, 100 %
- Purifikasi & Perbaikan Trafo 20KV, 80 %
- Cleaning Oil Cooler 1&2, 50%
- Cleaning Air Cooler Generator 100%
- Start Turbine 2, 0 % TANPA PADAM UNIT
- Cleaning Sand Filter, 100 %
- Perbaikan Pondasi Ring Hammer, 75%
Additional work
- Repair deck plate area isolator Esp#2, 50 %