Kondisi Pembangkit PLTU Baturaja 30 Mei 2023

A. Kondisi Operasi Mesin

STG 1 = OFF
STG 2 = ON (24 Jam)

B. Kondisi Maintenance

Progres Overhaul

PekerjaanProgress
A. Boiler 1100%
Stop Boiler (100%)100%
Cooling Booiler, ESP, drain debu Esp 1 (100%)100%
Cleaning Esp 1 (100%)100%
Pengecekan Isolator dan Heater Esp 1 (75%)75%
Pengecekan dan perbaikan Collcecting Plate dan Elektroda Boiler 1Proses
Perbaikan kebocoran Ducting dan Bracing Esp 1 (15%)15%
Cleaning Air Heater Boiler 1Proses
Penggantian Shaft Rapping Vesel 1Proses
Penggantian Thermocouple Combution Boiler 1Proses
Pengecekan dan penggantian valve Collection Header Boiler 1 DN 80 & DN 20Proses
Pengecekan (perbaikan) sensor level drum Boiler 1Proses
Cleaning Burner Boiler 1 100%100%
Cleaning nozle Furnice Boiler 1 (70%)70%
Cleaning Nozle Solar Boiler 1Proses
Start Up Boiler 1Proses
B. Turbine 1
Stop Turbine 1 (100%)100%
Pengecekan Oli Governoor (50%)50%
Pengecekan Steam Room GovernoorProses
Perbaikan sensor error di monitor CCRProses
Pengecekan (penggantian) Bearing Front Rear Turbine dan Generator (10%)10%
Set Aligment Shaft dan Coupling Turbine GeneratorProses
Perbaikan Flange gasket HPH Turbine 1Proses
Perbaikan pipa Drain main Steam Turbine 1Proses
Cleaning Condensore 1 (10%)10%
Cleaning Air Cooler 1 & 2 (100%)100%
Pengecekan dan Penggantian Bearing motor Exhaust Fan Turbine 1Proses
Pengecekan Generator STG 1Proses
Pengecekan Trafo STG 1Proses
Start Up Turbine 1Proses