Kondisi Pembangkit PLTU Baturaja 9 September 2023

Kondisi Operasi Mesin
STG 1 = ON (0-24)
STG 2 = ON (0-24)

Maintenance
Mekanik

  1. Maintenance pompa SC#1 (penambahan gland packing)
  2. Perbaikan pin arm governur turbine #1
  3. Lanjut pekerjaan fabrikasi suction pipe pompa ponton#2
  4. Repair kebocoran line transfer ash silo
  5. Lanjut install drain mini silo
  6. Perbaikan line transfer vessel #3

Elektrik

  1. Senam pagi
  2. Chek dan perbaikan discharge selenoid botol3 Esp
  3. Support mekanik Chek power las plasma ash silo
  4. Support dan pengawasan optimalisasi hoist crane dcs Dengan agenda kerja:
    1.Merubah kabel power karena putaran dinamo terbalik
    2.pasang sling ke bucket
    3.perbaikan brake naik turun bucket

SPB
Nihil

Switching Filter CPC Turbin#1 & turbin#2

Pengencangan pin governor hidrolik valve main steam turbin#1&2

Penggantian glend packing pompa SC#1

perbaikan brake hoist dcs

instal seling bucket

Team subkon, di bantu team PLTU perbaikan optimalisasi Hoist crane DCS 1