Kondisi Pembangkit PLTU Baturaja 18 Oktober 2023

Kondisi Operasi Mesin
STG 1 = ON (0 – 24 )
STG 2 = ON (0 – 24 )

Maintenance
Mekanik

  1. Cleaning area work shop
  2. Inspeksi All Weighing conveyor
  3. Inspeksi kompresor SULLAIR
  4. Repair kebocoran Hopper transfer weighing #2
  5. Inspeksi ESP
  6. Penambahan oil block bearing IDF.
  7. Melanjutkan pekerjaan penggantian plate bordes WTP.
  8. Pengecekan dan perawatan pompa multi stage : Pompa suply demin, UF, RO, Hp RO dan mixbed.
  9. Perbaikan Roller Screen 1A

Elektrik

  1. Continue perbaikan kabel control swas ( steam water analysis system)
  2. Pengecekan ACB Black start Genset 1000 KW, out going
  3. Perbaikan Lighting distribusi room
  4. Daily maintenance panel

SPB
Konsumable
Lokal
Mata gerinda potong 20 pcs

Leave a Reply

Your email address will not be published. Required fields are marked *