Kondisi Pembangkit PLTU Baturaja 28 Oktober 2023

Kondisi Operasi Mesin
STG 1 = ON (0 – 24 )
STG 2 = ON (0 – 24 )

Maintenance
Mekanik

  1. Cleaning area work shop
  2. Inspeksi All Weighing conveyor
  3. Inspeksi kompresor SULLAIR
  4. Lanjut perbaikan Roller Screen #1A
    modifikasi base plat Gear box (Sliding)
  5. Repair kebocoran line transfer Ash Silo
  6. Perawatan Ponton
    Fabrikasi screen belakang Ponton
    Pengecatan flintkote ponton.
  7. PM IDF
    Penambahan oil block bearing IDF #2 dan #4

Elektrik

  1. Senam sabtu sehat
  2. Perawatan Mcc room
  3. Chek temperature trafo Lv aux2

SPB
Nihil