Kondisi Pembangkit PLTU Baturaja 2 November 2023
Kondisi Operasi Mesin
STG 1 = ON (0 – 24 )
STG 2 = ON (0 – 24 )
Maintenance
Mekanik
- Cleaning area work shop
- Inspeksi All Weighing conveyor
- Inspeksi kompresor SULLAIR
Lanjut cleaning - Repair kebocoran line transfer Ash Silo
- Repair kebocoran ducting hopper weighing #4
- P/M. WTP
Penggantian plate lantai yg keropos di WTP
Fabrikasi flange joint 3″ untuk mengurai tanah di area ponton - ESP
Repair F/V Vessel #6 - Fabrikasi doubling plate elbow Ash silo ( 4 set ) untuk penggantian di area bottom main silo (belakang Compressor Room)
Elektrik
- Perawatan speed meter motor idf1-4
- Pemasangan cover tutup panel inverter ponton
- Perawatan grounding demin
- Pemasangan auto lampu pamp house
- Perbaikan pressure transmitter esp botol 6
- Pemasangan timer lighting elv 14
- Daily maintenance
SPB
Nihil