Kondisi Pembangkit PLTU Baturaja 14 November 2023
Kondisi Operasi Mesin
STG 1 = ON (0 – 24 )
STG 2 = ON (0 – 24 )
Maintenance
Mekanik
- Cleaning area workshop
- Inspeksi All Weighing conveyor
- Inspeksi kompresor SULLAIR
- Continue fabrikasi Knalpot W/L
Install - Maintenance WTP
Melanjutkan pemasangan plate bordes lanai WTP.
Perbaikan pompa dosing biocide.
Melakukan perawatan kompresor WTP - Repair R/S #1B
Ganti block bearing - Repair kebocoran line transfer ash silo
- Prepair penggantian skirt rubber pengarah mulut bunker elv.26.0
fabrikasi rubber skirt ex B/C - Inspeksi Wet Drain Mixer Main Silo
Bearing Failure
Elektrik
- Penggantian lampu scurity yg mati
- Abnormal pju depan office
- Continue repair motor Cwp1
- Abnormal Ac crusher
- Perawatan panel room Elv 7
- Daily pressure transmitter dan sensor vaccum boiler
SPB
Nihil