Kondisi Pembangkit PLTU Baturaja 2 Januari 2024
Kondisi Operasi Mesin
STG 1 = ON (0 – 24 )
STG 2 = ON ( 0 – 24 )
Maintenance
Mekanik
- Repair kebocoran pipa transfer dan Ashilo
- Repair gearbox rapping & Install
- Fabrikasi screen kompresor Sullair
- Cleaning
- -Cek weighing
- Repair kebocoran hover transfer botol#2
Elektrik
- Perbaikan Tempt Oil Tank Turbine 2
- Check Temp inlet Condenser T.2
- Merapikan solenoid valve ,panel botol esp
- Ganti lampu office
- Suport power team mekanik
- las pipa transfer
SPB
Nihil